Alta Vista Tank No. 2 Construction Update
Check out the latest update on the District's new 500,000 gallon water tank with interesting photos, facts and more.
Slideshow shows construction in progress on Alta Vista Tank #2.
Montara Water and Sanitary District Alta Vista Tank No. 2 Construction Update. Board of Directors Meeting. May 7, 2015.
Project Features. Capacity: 500,000 gallons. Type: Pre-stressed Reinforced Concrete. Partially (mostly) buried. Domed roof. Cost: $2.9M. Start: October 2014. Completion: December 2015.
Construction Progress. Shows image of base of tank formed.
Construction Progress. Shows image of base of tank rebar placed.
Construction Progress. Shows image of base of tank rebar placed.
Construction Progress. Shows image of base of tank cast April 20th.
Construction Progress. Shows image of base of tank cast April 20th.
Construction Progress. Shows image of seismic cables.
Construction Progress. Shows image of wall reinforcement.
Construction Progress. Shows image of wall reinforcement.
Construction Progress. Shows image of wall reinforcement.
Construction Progress. Shows image of wall forms.
Next Steps. Cast walls. Post tension walls. Hydro blast walls. Apply pre-stressing cable. Shotcrete application. Shows two links to youtube videos.
Construction Schedule Milestones. Tank walls: mid May. Tank roof: mid June. Backfill: mid August. Landscape: mid October. Completion: mid December.
Project Team. Montara Water and Sanitary District. SRT Consultants. Western Water Constructors, Inc. DN Tanks DYN and Natgun generations strong.